Construction Updates

  1. Home
  2.  » Construction Updates

Contact Us:  Please contact us with any questions or concerns about CV Link construction

Project Hotline: (833) 4CV-LINK (428-5465)

Email: info@coachellavalleylink.com

Latest Construction Updates: 

North Palm Springs

Highway 111 to Vista Chino

Work to be completed: Painting of shade structures, crack repairs, crosswalk signal improvements at Gene Autry and Vista Chino

Central Palm Springs

Ramon Road Undercrossing

Work to be completed: Grading pathway, install of rebar and placement of cement

E. Mesquite Ave at S. Farrell Drive

Work to be completed:  Install 3′ Extension for Bicycle Signal

South Palm Springs & Cathedral City

Ave 34th

Work to be completed:  Pedestrian push button repair, striping repair

Cathedral Canyon Dr

Work to be completed:  Pedestrian crosswalk and signal

Date Palm Undercrossing

Work to be completed:  Painting of name on bridge

La Quinta to Coachella

Jefferson

Work to be completed: Installation of cable railing

Miles Undercrossing

Work to be completed: Installation of striping and puck lights with projected completion of 11/21. Pathway is open during construction.  

Golf Club to Dillon Road

Work to be completed: Installation of traffic signal pole lights.

Dillon Road to Ave 50

Work to be completed: Installation of column lights and flashing stop signs.

Indio Blvd

Work to be completed: Installation of highwater detection system, striping, solar path lights, painting of undercrossing, and installation of canopy structure

Project wide

Work to be completed: Crack repair, sign installation, and safety enhancements