Latest Construction Updates:
Palm Springs & Cathedral City
Ramon Road Bridge
Work to widen the existing bridge over the Whitewater Channel is expected to start Fall 2026 with completion in 2029. CV Link under Ramon Road will be closed for the duration of the project. A detour will be posted around the construction zone.
Indio
Interstate 10 / Monroe Street Interchange
Work to upgrade the interchange is expected to start January 2027 with completion in 2029. CV Link under Monroe Street will be closed for the duration of the project. A detour will be posted around the construction zone.
Coachella
Avenue 50 at the Whitewater Channel
Work to construct a new bridge over the Whitewater Channel is expected to start August 2026 with completion in 2028. CV Link at Avenue 50 will be closed for the duration of the project. A detour will be posted around the construction zone.